The developer says "it's not a bug". What do you do?

First compare the behaviour with the source of the expected result (the test oracle): a requirement, mockup, API specification or standard. If the requirement is clear, the argument ends with the comparison. If it is silent or ambiguous, the PO or PM decides and QA prepares options. The decision is recorded in the ticket and the requirement. “By design” is not “good for the user”: such cases are filed as improvements.

QA Fundamentals · Bugs and bug reports

The developer writes "works as designed", but you are sure it is a bug. What next?

A user changes a password, and their session on another device stays alive. QA files a bug, the developer answers "it is not a bug, it is by design", QA insists, and for three more days the discussion goes round in circles, comment after comment. Nobody gets any further and the ticket hangs. This lesson is about why such arguments arise, how to get out of them with facts instead of "that is how I see it", and who has the final word.

How it works and why. The "bug or not a bug" argument is really an argument about what counts as correct. The expected behaviour does not live in the head of QA or the developer: it has a source. ISTQB calls it a test oracle, a source to determine the expected result. Such a source can be a requirement or a user story with acceptance criteria, a mockup, an API specification, a standard (HTTP, WCAG), the behaviour of a previous version, similar screens of the product, a decision made by the PO. When the source exists and is unambiguous, the talk is short: the fact is compared with it. When it does not, everyone considers correct what they themselves expect, and the talk never ends. That is why the first step is always checking the source, not proving yourself right.

Three situations after "it is not a bug"

"Not a bug": check the requirementRequirement clear,bug is realShow requirementand evidenceRequirement clear,I was wrongClose as Not a bug,say thanksRequirement silentor ambiguousAsk the PM/PO,record the decision
Figure 1. The requirement decides everything. Sometimes QA is right, sometimes the developer, and sometimes there is no answer, and then the decision belongs to the product.

Each branch has its own action. If the requirement is clear and the bug is real, show it with the fact and evidence: a quote, a screenshot, a request and response. If the requirement is clear and the developer is right (it happens that QA read an old version or understood it inexactly), the ticket is closed as Not a bug, and QA updates their knowledge and test cases. That is a normal part of the work, not a defeat. If the requirement is silent or allows two readings, neither side has the right to decide alone: the question is addressed to the PM or the PO, who are responsible for the expected behaviour of the product. QA lays out options and consequences, not "who is right".

Example: from an argument to a decision.

Before:
  Dev: Not a bug, that is how it works.
  QA:  No, it is a bug.
  (six more comments)

After (the QA comment):
  Requirement: PAY-142, item 3.1 "the amount is accurate to the cent".
  Fact: 100.555 → POST /api/transfers → 500, screenshot and HAR attached.
  Unclear: item 3.2 is silent on whether to round or reject the input.
  Options: (A) reject with a hint, (B) round to 100.56.
  @PO: which option? Either way a 500 is unacceptable.
Decision (PO, 20 Nov): option A. Requirement item 3.2 is extended,
  test case TC-88 is updated.

How to read it. In "Before" both sides assert, but nobody shows a source, so the argument has no end. In "After" QA starts with the requirement and quotes it, gives the fact with evidence, singles out what is unclear in the requirement and offers options. After that the ticket has an addressee and a question with answer options. The PO's answer is recorded in the ticket, the requirement is extended, the test case is updated. A month later, when nobody remembers the argument, the answer is in the ticket history. Look separately at the last line of QA: even if the PO picks option B, a 500 in response to valid input remains a problem. A decision about the expected behaviour does not cancel defects outside it.

Limits and alternatives. "Works as designed" does not mean "good for the user". Verification answers "is what was designed built", validation answers "is it what users need" (the difference is in the lesson on verification and validation). If the behaviour matches the requirement but harms the user, it is no longer a bug but a change proposal: file it as a separate ticket of the improvement type with a justification, not as a bug. When there are no requirements at all (a startup, a quick prototype), rely on reasonable user expectations, consistency with other screens and experience of similar products, and escalate the question anyway. There are exceptions: if the "not a bug" concerns security or data loss, QA does not leave the ticket without a decision but escalates it. To make such arguments rarer, hold a requirements discussion before development (three amigos: PO, developer and QA) and require stories to meet the Definition of Ready: clear acceptance criteria remove most questions in advance.

Common mistakes.

  • Arguing without a source: "I think" against "I think" has no winner and costs days.
  • Treating the talk as a contest: the aim is not to win the argument but to find out what counts as correct.
  • Deciding for the PO: QA or the developer decided that "it is better this way" and changed the behaviour without agreement.
  • Not recording the decision in the ticket: a month later someone else files the same bug again.
  • Silently accepting "not a bug" although the defect clearly harms: the risk question should have been raised and settled with the PO.
  • Not updating the requirement and the test case after the decision: the mismatch will come back.

Check yourself

The requirement says "the user must receive a confirmation email". The email arrives after 25 minutes. The developer: "the email arrives, not a bug". What do you do?

Answer

The requirement gives no time, so this is an ambiguity. I collect facts (send and receive times, mail service logs), and propose that the PO clarify an acceptable delay (for example, within a minute) and give options. Until there is a decision, the ticket stays with a question to the PO and is not closed. After the answer the requirement is extended and a check is added.

Why does QA first check the requirement in response to "it is not a bug" instead of giving more evidence of being right?

Answer

Because without a source of the expected behaviour evidence proves nothing: a screenshot shows what happens, not what should happen. Checking may reveal that I was wrong (then I save everyone time) or that the requirement is incomplete (then it is a question for the PO). Either way the talk moves from opinions to a document.

In an interview. Junior: First I check myself against the requirement and the mockup. If the requirement is clear, I show it and the evidence. If it is ambiguous, the question goes to the PM, because the product defines the expected behaviour, not me and the developer. I record the decision in the ticket. Middle/Senior: I see this as a question about the test oracle: is there a source of the expected behaviour. If the requirement is clear, the argument ends with a comparison. If it is silent, I do not fight but prepare options with consequences for the PO, record the decision, and then update the requirement and the test case. "Works as designed" does not yet mean "good for the user", so such cases are handled as an improvement. To have fewer arguments, I support requirements discussion before development and clear acceptance criteria in the Definition of Ready.