What are Definition of Ready and Definition of Done?
The Definition of Ready describes when a story is ready to be taken into work: clear requirements, acceptance criteria, an estimate. The Definition of Done describes when work is complete and can join the increment. In ISTQB terms these are entry and exit criteria. DoD is in the Scrum Guide, DoR is a team practice. Acceptance criteria belong to one story, DoD is shared, and Done needs both.
QA Fundamentals · Processes and Agile
A story reached testing without acceptance criteria. Whose problem is it: QA or the team?
QA picks up the story "Transfers between cards" and does not know what to check: the ticket has one sentence, there is no mockup and the limits are "to be clarified". At the end of the sprint the developer writes "done" and QA finds that an amount with three decimals gives a 500. Who should have noticed earlier, and what exactly was "done"? For such conversations teams agree on two shared lists: the Definition of Ready and the Definition of Done. This lesson is about what they mean, how they differ from acceptance criteria and how QA uses them.
How it works and why. The Definition of Ready (DoR) describes when a story is ready to be taken into work: clear requirements, acceptance criteria, mockups, an estimate, known dependencies. The Definition of Done (DoD) describes when work on a story is complete so that it can be added to the increment. In ISTQB terms these are entry criteria (the conditions under which an activity may start) and exit criteria (the conditions under which it can be considered complete), and for agile the CTFL 4.0 syllabus names them directly as Definition of Ready and Definition of Done.
Their status in Scrum differs. The Definition of Done is in the Scrum Guide: it is a formal description of the state of the increment when it meets the quality standards, and if the organisation has a common DoD, the team adopts it as a minimum. The Definition of Ready is not in the Scrum Guide: it is a team agreement that took hold as a practice. So in an interview it is correct to say "DoD is part of Scrum, and DoR is a common team practice".
Two checks on a story's path
| Acceptance criteria | Definition of Done | |
|---|---|---|
| What it applies to | One story | All the team's stories |
| The question it answers | What exactly must this feature do? | What else must be done for this to be complete? |
| Example | "An amount with 3 decimals is rejected with a hint" | "Code review passed, regression done, documentation updated" |
| Who agrees on it | The PO with the team at refinement | The whole team (and the organisation, if there is a common DoD) |
A story is Done only when both its acceptance criteria and the whole DoD are met. So "the feature works" is not yet "done": you can have correct code with no regression and no updated release notes.
Example: from a story that cannot be verified to one that can. The initial version:
Story: As a customer, I want to transfer money between my own cards.
(No mockup, limits "to be clarified", estimate: 5.)
There is nothing to test against. Every sentence raises a question: which cards, which limits, what to show on a decline. This is exactly what the DoR is for: it is not bureaucracy but a way to catch questions before the story gets into the sprint. At refinement QA turns them into criteria:
Story: As a customer, I want to transfer money between my own cards
so that I do not have to visit a branch.
Acceptance criteria:
1. An amount from 0.01 up to the available balance, accurate to the
cent; extra decimals are rejected with a hint.
2. A transfer to the same card is forbidden, error text per mockup.
3. After success both balances are updated, history has one entry.
4. The issuer bank declines: no money is debited, the user sees why.
Mockup: the "Transfer" screen (link). Limits: requirement PAY-142.
Dependencies: the transfer API is ready on stage; test cards needed.
Now the story shows what counts as correct: the first criterion directly covers the three-decimals bug that would otherwise be found at the end. When checking the DoR, QA asks: are there criteria that can be verified? are the data and the environment known? does the estimate include testing? Only then does the story go into the sprint.
The exit is served by the DoD. An example of a team list:
Definition of Done (an example for a team):
[ ] Code is in main, code review passed
[ ] Unit and API tests written, the pipeline is green
[ ] Acceptance criteria verified on stage
[ ] Regression around the changed modules done
[ ] No open critical bugs
[ ] Documentation and release notes updated
QA is responsible for several lines here: verifying the criteria, regression and the absence of critical bugs. The principle is that every DoD item must be verifiable: "quality is ensured" cannot be checked, while "regression around the changed modules is done" can be shown with a run result. If even one item is not met, the story is not Done and is not carried into the report as "almost done".
Limits and alternatives. A DoR is easy to turn from a help into a barrier: if it is read as a contract ("not per DoR, I won't take it"), the team starts arguing about form instead of discussing requirements. So a DoR is usually kept as a short checklist, not a formal obligation, and with flexibility: a small story can be taken with incomplete criteria if the team knowingly accepts the risk. A DoD must not demand the impossible ("zero bugs"): the list must be realistic and refined at retros over time. Sometimes several levels are kept: a story DoD, a sprint DoD and a release DoD, where the release level has, for example, full regression or UAT. There are organisation-level DoDs, and a team can only tighten them. In Kanban the DoR and DoD are also useful as column policies, even though there is no word "sprint" there.
Common mistakes.
- Taking a story without acceptance criteria into the sprint: QA has to guess the expected result and the developer codes "by eye".
- A DoD without verifiable items ("code is of good quality"): it can neither be met nor violated, so it does not work.
- Closing a story when the criteria are met but the DoD is not: regression and documentation are postponed "for later" and build up debt.
- Mixing up acceptance criteria and the DoD: the first are about the function of a particular story, the second about the general standard of completion.
- Using the DoR as an excuse to refuse work instead of as a signal to discuss an unclear point.
- Never updating the DoD: if bugs slip through regression every time, an item about regression or automated tests is worth adding.
Check yourself
The developer writes: "The story is done, all acceptance criteria work". Can it be closed? What do you check?
Answer
Not necessarily. A story is Done only when both the acceptance criteria and the DoD are met. I check the remaining DoD items: whether code review is passed, whether there are automated tests and a green pipeline, whether regression around the changed modules is done, whether there are open critical bugs, whether documentation is updated. If something is missing, the story stays in progress or moves on with an explicit agreement.
Why should the Definition of Ready not be applied as a rigid contract "not per DoR, I won’t take it"?
Answer
Because the DoR is a team practice, not a Scrum requirement, and its purpose is to expose ambiguities before work starts. Rigid use turns it into a formality and a conflict: the sides argue about matching the list instead of about requirements. A checklist with flexibility is better, where the team can knowingly take a story with a known risk.