What should be in a test report?
A test report must let readers make a decision: what was tested and on what, how it ended, what stays open and risky, and what is recommended. It goes from the conclusion to the evidence. Defects by severity, blocked cases and untested scope are listed separately, because a pass percentage alone proves nothing. A progress report shows the course of work, a completion report the outcome and residual risks.
QA Fundamentals · Test documentation
A manager asks “Can we release?” and you answer with a 40-row table. What should they hear instead?
On Friday evening testing is done and QA sends a report: 212 rows, coloured charts, percentages. The product manager asks one thing: “So can we release?”. The table has no answer, and the decision is made blindly or postponed. A report exists for a decision, not to show that work was done. Below: what it must contain, how the progress and completion reports differ in ISTQB, and what a report people actually read looks like.
How it works and why. A report reader did not watch the testing and has no time to dig through it. So the report goes from the conclusion to evidence: what was tested and on what, how it ended, what stays open and risky, what we recommend. ISTQB (CTFL 4.0, section 5.3) distinguishes two kinds. A test progress report comes out regularly during the work: the period, progress against the plan, impediments and workarounds, metrics, new and changed risks, what is planned next. A test completion report is prepared at the end of a level, iteration or project: a summary of what was done, deviations from the plan, status against exit criteria, defects, residual risks, lessons.
A report block and the reader’s question
Worked example: from a table to a decision. A typical weak report: “212 cases executed, 89% passed”. It does not show that among the remaining 11% there is a critical defect and that 15 cases did not run (6 blocked, 9 not executed because the gateway was down). A report of the same run that helps to decide:
Test report: release 2.14 "Daily limits", build 2.14.0-rc2
Environment: staging, 18-20 Nov; manual cases and API automation
Result: 212 cases: 188 passed, 9 failed, 6 blocked,
9 not executed (the gateway was down on 19 Nov)
Open defects: 1 critical (BUG-412: the limit does not reset
at 00:00), 2 medium, 5 low
Not tested: currency transfers (moved to 2.15), load
Risk: the day rollover may leave a user without a limit
Recommendation: do not release while BUG-412 is open.
Conditions for Go: the fix, a rerun of the 6 blocked and 9 not
executed cases, a check at 23:59 and 00:00.
Two reports about the same run
A table of numbers
89% passed, a chart by day, 40 rows of cases. The reader decides alone whether 89% is good and does not see the critical defect and the untested part.
A conclusion and evidence
The recommendation comes first: do not release while BUG-412 is open. Then the result, defects by severity, what was not tested, conditions for Go.
Limits and alternatives. A report does not make the release decision: QA gives an assessment and a recommendation, and the product owner or management decides. The pass percentage is misleading: 98% may mean the only critical path failed. So defects by severity and the untested scope are placed next to it. In a live Agile process part of the report is replaced by a dashboard with the CI run and Allure or a similar tool, and the summary is written briefly in the release ticket. For progress reports a few lines daily or weekly are enough: what is done, what blocks, what next.
Common mistakes.
- Starting with numbers and hiding the conclusion at the end: the reader never gets to it.
- Not saying what was not tested: silence is read as “all is fine”.
- Counting blocked cases as passed or not mentioning them at all.
- Confusing a recommendation with a decision: “you must postpone the release” instead of “the risk is this, I recommend that”.
Check yourself
A report shows 98% of cases passed and the author writes “ready for release”. What else is needed before that claim can be accepted?
Answer
Defects by severity (did the critical path fail among the 2%), blocked and unexecuted cases, untested scope and risks. Without this the percentage says nothing about readiness.
How does a progress report differ from a completion report?
Answer
A progress report comes out regularly during testing and shows progress, impediments and the plan for the next period. A completion report is prepared at the end of a level or project: summary, deviations from the plan, status against exit criteria, residual risks and lessons.